Home  >  Support  >  Support Forum  >  increase awakeTime in sync cyclic sleeping network

increase awakeTime in sync cyclic sleeping network

0 votes
HI,

i'm tryng to implement ota in a digimesh cyclic sleeping network, i have 3 motes(waspmote v1.1) that are configured as synchronous cyclic sleep Mode (SM=8) and the gateway as coordinator.
When i want update the motes i change the awake time(15 min.) on the coordinator and after a sleep/awake cycle the motes are synchronized and i can start with otap update, but there is a more efficient way to manage otap update in this scenario??

Is possible change the sleep mode or better increase the waketime when i recieve the first ota pkt??
asked Mar 20 in DigiMesh Proprietary Mesh Networking by pie82 New to the Community (2 points)

Please log in or register to answer this question.

2 Answers

0 votes
Not that I know of. Sounds like you have a working protocol.
answered Mar 24 by MikeN Community Contributor (80 points)
0 votes
Thanks for reply MikeN,

yes it works... but i want know if there is a way to increase ST window instantly and not after a sleep/wake cycle...
Another question... do you know if is possible handle the sync message sent from coordinator to other motes??
answered Mar 26 by pie82 New to the Community (2 points)